Another important Landmark has been achieved at #SukiKinari Hdyropower Project (884MW)Today 30th April, 2021 at about 110hrs, River #Kunhar has been diverted through Spillway bays to start the filling of Asphalt core, Rockfill dam. To Celebrate this, a ceremony has been held at construction site and the representative of all stakeholders participated. Congratulation to all and salute to those who have worked day and night to make this happen.
ISLAMABAD, Apr 30 (APP): CPEC Authority Chairman Lt Gen (Retd) Asim Saleem Bajwa Friday said that about 60 percent work of the Suki Kinari Hydro Power Project had been completed.
He said the project that is being executed under the framework of China Pakistan Economic Corridor (CPEC) would become operational in December 2022.
#CPEC: Secondary River Closure Ceremony of 884 MW Suki Kinari Hydro Power Project, 2 Billion USD, 60% work completed, expected completion December 22, Location: River Kunhar, Kagan 1/2 #CPECMakingProgress #PakistanMovingForward pic.twitter.com/7j7nQfqjz0
— Asim Saleem Bajwa (@AsimSBajwa) April 30, 2021
In his tweet after attending the Secondary River Closure ceremony of the 884 MW hydro power project, the CPEC Authority chairman said the project was located at River Kunhar, Kaghan and the total cost of the project was US$2 billion.